Dubai Metro Blue Line Progress: 29% Complete as New Trains Are Unveiled
The Dubai Metro Blue Line passed another public milestone on 22 November 2026. During a visit to the Blue Line worksite in Dubai Festival City, His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, was briefed that the project is now 29% complete. He also reviewed the new train design for the line, the interior concepts for its 14 stations and the engineering work on the line’s bridge across Dubai Creek.
The update came from the Government of Dubai Media Office and the Roads and Transport Authority (RTA). It confirms that work is on track for the opening date RTA has given since May: 9 September 2029, the 20th anniversary of the Dubai Metro.
This article sums up what was announced, what the Blue Line will connect, how the project has moved since 2023 and what the news means, and does not mean, for people who own or plan to buy property in Dubai.

What was announced on 22 November
According to the Media Office release, the visit covered five main topics:
- Construction progress: overall completion of 29%, with more than 14,000 workers having put in over 33 million working hours.
- New trains: the design and smart systems of the trains that will run on the Blue Line.
- Station interiors: five architectural concepts for the line’s 14 stations.
- The Dubai Creek bridge: how the Metro’s first crossing over the Creek is being built.
- Rail technology: a train-systems simulation laboratory built with CASCO Signal, an AI-based rail inspection system developed by RTA’s Rail Agency, and the next generation of nol payment cards.
The project is being delivered by the MAPA–LIMAK–CRRC consortium, which won the AED 20.5 billion contract (about USD 5.58 billion) in December 2024.
Blue Line progress in numbers
RTA broke the overall figure down by type of work:
| Work package | Completion (22 Nov 2026) |
|---|---|
| Overall project | 29% |
| Tunnel excavation | 55% |
| Underground stations | 32% |
| Elevated stations | 16% |
| Bridge works | 17% |
| Bridge piers | 62% |
For context, when tunnelling began on 3 May 2026, RTA said the project was 20% complete and was expected to reach 30% by the end of 2026. At 29% in late November, the project is close to that year-end target. Tunnelling and underground work are furthest ahead, while the elevated stations and bridge decks have the most work left.
The new Blue Line trains
The train shown to the Crown Prince has a design capacity of 675 passengers and a total capacity of 1,246 passengers per journey. RTA describes an exterior that draws on “strength, speed and streamlining”.
Inside, the trains keep the familiar Dubai Metro layout of three cabin types:
- Gold Class, with contemporary seats, wireless chargers for phones, digital screens, lighting that adjusts to ambient conditions and a ceiling designed to look like a star-filled sky.
- Silver Class, arranged for capacity and easy movement, with large windows and dynamic route screens.
- A dedicated carriage for women and children.
The trains also carry smart systems: cameras that detect obstacles on the track, cameras that count passengers and monitor how full each carriage is, and real-time data processing. RTA says this will help it manage capacity and run services more efficiently.

Station designs and the Creek bridge
Five station concepts. The Crown Prince reviewed interior designs for the Blue Line stations. One is the Emaar Properties Station at Dubai Creek Harbour, inspired by the idea of a “crossing gateway”. RTA has said this station will rise 74 metres, making it the world’s highest metro station. The other four designs are inspired by the natural elements of water, air, fire and earth.
Dubai Creek bridge. The Blue Line will be the first Metro line to cross Dubai Creek, on a 1.3 km bridge. RTA explained that the bridge is built from precast concrete segments. These are cast in a yard near the Creek and installed from the completed piers, which reduces the need for floating cranes and keeps boat traffic moving during construction.
Where the Blue Line will run
RTA’s published route has not changed. The line is 30 km long, with 15.5 km underground and 14.5 km elevated, and 14 stations. It has three interchange stations: Creek (Al Khor) on the Green Line, Centrepoint on the Red Line, and International City 1, where the line’s two branches meet.
- Branch one (21 km, 10 stations): from Creek Station in Al Jaddaf through Dubai Festival City, Dubai Creek Harbour and Ras Al Khor to International City 1, then on to International City 2 and 3, Dubai Silicon Oasis and Dubai Academic City.
- Branch two (9 km, 4 stations): from Centrepoint Station in Al Rashidiya through Mirdif and Al Warqa’a to International City 1.
The Media Office describes these as fast-growing areas and links the project to the Dubai 2040 Urban Master Plan, which encourages development around public transport stations. RTA says the line will serve areas with more than one million residents. In its May release, it also said the line would offer journeys to Dubai International Airport of around 20 minutes from areas along the route and cut traffic congestion on the corridors it serves by around 20%.

How the project has moved since 2023
According to RTA and the Media Office, the main milestones are:
- November 2023: the Blue Line route is approved.
- December 2024: the AED 20.5 billion contract is awarded to MAPA–LIMAK–CRRC.
- June 2025: the foundation stone is laid.
- 3 May 2026: tunnelling works begin; the project is 20% complete.
- 22 November 2026: the project is 29% complete and the new trains and station designs are reviewed.
- End of 2026: target of 30% completion.
- 9 September 2029: planned opening.
The Blue Line is separate from the Dubai Metro Gold Line, a fully underground 42 km line approved in April 2026 with a planned opening on 9 September 2032, and from the Metro extension to Al Maktoum International Airport City approved by Dubai’s Executive Council on 10 November 2026, which we covered in our real estate market study article.
What it means for property buyers
Steady progress on schedule. The headline figure matters because buyers often weigh future transport links when they choose a district. A project that keeps hitting its published targets is easier to plan around than one that slips. Even so, the opening is still almost three years away, and dates can change.
Areas along the route. The communities named by RTA include Dubai Creek Harbour, Dubai Festival City, International City, Dubai Silicon Oasis, Dubai Academic City, Mirdif and Al Warqa’a. Several new projects in these areas mention the Blue Line in their marketing, and some are being planned around the stations themselves. In Dubai Silicon Oasis, for example, the Dubai Integrated Economic Zones Authority (DIEZ) says the first phase of its Block 14 district, next to the future station, is due in 2029, in line with the line’s opening.
What the news does not tell you. The release does not give fares, station opening hours or the exact walking distance from any building to a station. It also says nothing about property prices or rents. We do not publish forecasts of price growth near stations, and buyers should be cautious with marketing that promises a fixed uplift from the Metro.
Practical checks before you buy near the Blue Line:
- Station location: check RTA’s published route map and confirm how far the building actually is from the planned station entrance, not just from the station name.
- Construction impact: homes close to elevated sections, stations or the depot may face several years of nearby works, noise and road diversions before 2029.
- Handover timing: if you buy off-plan, compare the developer’s handover date with the line’s planned opening and check the project’s escrow registration with the Dubai Land Department (DLD).
- Real transaction data: use DLD’s open data and the Dubai REST app to see recent sale and rental transactions in the building or community, rather than relying on advertised figures.
- Service charges: ask for the current or expected service charges and compare them with DLD’s official service charge index where available.
Interested in the districts along the Blue Line? Read our Dubai Academic City, Al Jaddaf and Dubai Creek Harbour guides, browse all properties, or talk to the Mina Prime Properties team.
Sources
- Government of Dubai Media Office: Hamdan bin Mohammed reviews Dubai Metro Blue Line progress and new initiatives (22 November 2026) and Mohammed bin Rashid inaugurates tunnelling works for the Dubai Metro Blue Line (3 May 2026)
- Roads and Transport Authority: Dubai Metro Blue Line project and Announcing the awarding of the Dubai Metro Blue Line project
- Roads and Transport Authority: Mohammed bin Rashid approves Dubai Metro Gold Line (April 2026)
- Government of Dubai Media Office: Mohammed bin Rashid launches AED12.8 billion strategic expansion projects for Dubai Silicon Oasis (22 January 2026; Block 14)
- The National: Dubai Metro Blue Line train design unveiled with Dh20.5bn project nearly 30 per cent complete (22 November 2026)
- Dubai Land Department: Real estate open data
This article is general information based on the sources above, checked on 23 November 2026. It is not financial or legal advice. Opening dates, routes and station designs depend on official decisions and may change. USD figures marked “about” are approximate at 1 USD = 3.6725 AED. Rental income and capital growth are not guaranteed. Verify details with RTA and the Dubai Land Department before you decide.